Finnish utility plans job cuts following nuclear reactor delay

Thursday, January 8, 2015

HELSINKI Jan 8 (Reuters) - Finnish nuclear power consortium Teollisuuden Voima (TVO) on Thursday said it is looking to cut up to 110 jobs, or 13 percent of its staff, due to lower power prices and soaring costs from its delayed Olkiluoto 3 reactor project.

The start of the reactor, planned to be Finland's fifth and biggest nuclear unit, has been delayed until late 2018, almost a decade later than originally planned.

"Electricity market price has dropped and there are no signs of improvement in the coming foreseeable future. In addition, costs related to nuclear power production have increased and the delay of Olkiluoto 3 project has caused remarkable additional costs," TVO chief executive Jarmo Tanhua said in a statement.

Posted in | »

UK accused of hypocrisy over plans to limit enforcement of EU climate goals

Wednesday, January 7, 2015

British lobbying to reduce monitoring of EU countries’ action on climate change has sparked outrage among MEPs and environmentalists.

EU states agreed last October to cut their carbon emissions 40% by 2030, but a UK plan co-authored with the Czech Republic proposes that countries’ emissions cuts should only be overseen with a ‘light touch’ regime with a diminished role for Brussels.

Posted in | »

Austrians resist EU funding for UK's Hinkley Point nuclear project

Thursday, December 18, 2014

Austrian premier Werner Faymann will today (18 December) protest at the British inclusion of landmark nuclear energy projects – including Hinckley Point – within its list of infrastructure eligible for funding under the proposed €315bn Juncker investment plan.

The UK has listed several nuclear-related projects within the Juncker plan, a list of 2,000 projects drawn from across all member states, which will be considered for funding under the investment plan.

Posted in | »

Germany wants to ringfence nuclear plant closure money-paper

Wednesday, December 17, 2014

BERLIN, Dec 17 (Reuters) - Germany plans to set up a fund to ringfence 17 billion ($21.2 billion) euros nuclear power firms have set aside to cover the long-term costs of decommissioning plants, Sueddeutsche Zeitung newspaper reported on Wednesday.

There has been concern in Germany that taxpayers could foot part of the bill to shut the plants because the money put aside by the firms to cover decommissioning costs could be lost in the event of a bankruptcy, or used for something else.

Posted in | »

Russia to extend US$270m export credit to Armenia for extending nuclear power operation

Thursday, December 4, 2014

(Armenian News, Yerevan, 19 November 2014) Armenia has approved a proposal for the extension of an Armenian-Russian intergovernmental agreement on cooperation extending the operation of the 2nd power unit of the Armenian nuclear-power plant (NPP). Armenia’s Minister of Energy and Natural Resources Yervan Zakharyan noted that, under the agreement, Russia is to extend a $270m export credit to Armenia.

Armenia said Sept. 13 it would extend the life of its ageing nuclear power plant, despite safety concerns over the Soviet-era facility in an active seismic zone.

Posted in | »

INES-event
INES 0

Event during operation of Zaporizhzhya NPP Unit №3

On 28 of November 2014 at 19:24 the disconnection of the Unit №3 of Zaporizhzhya NPP from power grid occurred. According to the preliminary information the cause of the occurrence was the failure of electrical equipment in the turbine hall.
As of 3rd December 2014 the reactor facility remains in the “cold” shutdown.
According to the preliminary evaluation this situation is qualified according to INES scale – “0-deviation (No Safety Significance)”.

Category: Power Reactor Ukraine Zaporizhzhia »

INES-event
INES 2

Realizing of maintenance activities without respecting the procedures

During maintenance activities that were conducted on some systems of one of the two irradiators present in the Sterigenic's installations, it was found that some safety-related equipment was unavailable. However, the availability of this equipment is requested as described in the procedure currently in application.

As this equipment was unavailable, Sterigenic's operators carried out those maintenance operations with only one safety device ensuring protection from a potential irradiation by the 60-Co sources that are used in the installations.

Category: Irradiation/Accelerators Facility Belgium »

Areva rethinks strategy after ditching targets

Thursday, November 20, 2014

PARIS (Reuters) - Areva must consider radical restructuring options after it abandoned financial targets in the face of continuing delays, writedowns and losses from its nuclear operations, analysts said, after the firm's shares plunged on Wednesday.

The state-owned group issued a third profit warning in four months, said it would review its funding options and dropped its 2015-16 financial targets, blaming delays to its Finnish Olkiluoto reactor, the slow restart of Japan's reactors and a lackluster nuclear market.

Posted in | »

Areva-Siemens raises claim to $4.4 billion over Finnish reactor delays

Tuesday, October 28, 2014

(Reuters) - The French-German consortium Areva-Siemens, the supplier of Finland's much-delayed Olkiluoto-3 nuclear reactor, has increased its claim against Finnish utility Teollisuuden Voima (TVO), TVO said late on Friday.

TVO and Areva have traded accusations about who is to blame for delays and extra costs, and the International Chamber of Commerce's (ICC) arbitration court is processing a dispute on cost overruns between the two sides.

Areva-Siemens in September said the start date of the reactor, which is planned to be Finland's fifth and biggest nuclear unit, will be pushed back to late 2018 - almost a decade later than originally planned.

Posted in | »

Chinese Company to Build Romania Nuclear Reactors

Monday, October 20, 2014

Nuclearelectrica, the company that runs Romania’s sole nuclear power plant, located in Cernavoda, has chosen China General Nuclear Power Corporation (CGN) as its investor for the development of two new nuclear reactors.

The project is worth of some 6.5 billion euro, according to company sources.

The Chinese company was the only bidder in the tender procedure organised by Nuclearelectrica.