Flamanville

Government to rip up rulebook and subsidise new nuclear plants

Monday, October 22, 2012

The Government is planning to write a "blank cheque" to the nuclear industry by underwriting the cost of new power stations, leading energy academics have claimed in a letter to The Independent.

Under a major policy U-turn being considered by ministers, the taxpayer would be left to cover the cost of budget over-runs or building delays at new nuclear plants. Costly setbacks are almost inevitable with such complex construction projects.

Posted in | »

Wind taken out of nuclear powers sails

Friday, August 3, 2012

It is one thing for a green pressure group to claim nuclear power is too expensive, but quite another when the charge comes from the head of an atomic industry pioneer such as General Electric.

GE built some of the world's first commercial atomic reactors in the 1950s and has remained an industry leader since its nuclear joint venture with Japan's Hitachi in 2007.

Posted in | »

EDF delays Flamanville 3 nuclear project again

Monday, August 22, 2011

PARIS, July 20 (Reuters) - EDF has delayed the completion of its first French next-generation EPR nuclear reactor by another two years to 2016, saying it expects the project's costs to rise to 6 billion euros ($8.52 billion).

In July 2010, the state-controlled utility had delayed the commercial start of the 1,600 megawatt nuclear reactor by two years to 2014. It had also previously raised its cost estimate for the project in northern France by almost 2 billion euros to 5 billion euros.

Posted in | »

Bulgarians, Romanians Building Nuclear Reactor in France Face Ruthless Exploitation

Wednesday, January 12, 2011

The foreign workers – including many Bulgarians and Romanians – on the construction site of EDF's new-generation nuclear reactor in Flamanville – face severe working conditions, according to French media.

Some one-third of the total number of 3 200 workers of the French state energy company EDF on the site in Flamanville are foreigners – mostly Romanians and Bulgarians but also Spanish and Portuguese, reported French news site Europe 1 citing the France Soir newspaper.

Posted in | »

France's EDF designs reactor to challenge Areva: report

Wednesday, October 6, 2010

PARIS - French electricity generator EDF is working on two new nuclear reactor designs of its own which could rival those made by Areva, the world's biggest atomic energy company, the Expansion magazine said.

In a report to appear Wednesday, Expansion said EDF is "looking at its own series of reactors," power rated at 1,000 and 1,500 Megawatts, which if finalised could be competition for Areva's third generation European Pressurised Reactor (EPR) and its Atmea design.

Posted in | »

EDF's EPR Reactor at Flamanville Is Delayed by 24 Months, Le Figaro Says

Tuesday, July 6, 2010

Construction of Electricite de France SA’s EPR nuclear reactor at Flamanville in Normandy is running about 24 months late, Le Figaro reported, citing an unidentified person.

EDF’s director in charge of the project, Herve Machenaud, responded that progress is still being evaluated, the newspaper said.

Posted in | »

Nuclear regulators in Europe, US to caution against EPR piping

Thursday, April 8, 2010

Nuclear safety authorities in four countries are assessing the significance of undocumented welding on primary circuit piping for the EPR reactor under construction at Olkiluoto-3, Petteri Tiippana, director of the nuclear reactor regulation department at the Finnish Radiation and Nuclear Safety Authority STUK, told Platts in an interview Thursday.

But Tiippana said that contrary to a statement made Wednesday by Marie-Pierre Comets, a commissioner of French nuclear safety authority ASN, regulators from Finland, France, the UK and the US are not preparing a joint statement on the piping qual

Posted in | »

In Finland, Nuclear Renaissance Runs Into Trouble

Friday, May 29, 2009

OLKILUOTO, Finland — As the Obama administration tries to steer America toward cleaner sources of energy, it would do well to consider the cautionary tale of this new-generation nuclear reactor site.

The massive power plant under construction on muddy terrain on this Finnish island was supposed to be the showpiece of a nuclear renaissance. The most powerful reactor ever built, its modular design was supposed to make it faster and cheaper to build. And it was supposed to be safer, too.

Posted in | »

Rebound of nuclear plants raising worries over waste

Friday, January 30, 2009

BRUSSELS — BRUSSELS: As France presses ahead with building more next-generation nuclear reactors, new evidence emerged Friday to suggest that industry and governments may be unprepared to handle the increasingly toxic waste that will result.

Highlighting the importance of the technology in France, both as its main source of electricity and as a major export industry, President Nicolas Sarkozy of France announced late Thursday that Électricité de France, Europe's biggest power producer, was awarded the contract to develop a second atomic reactor using next-generation technology.

Posted in | »

Normandy Dairy Towns Challenge EDF on Nuclear Reactor

Thursday, December 11, 2008

Dec. 10 (Bloomberg) -- The lush green hills overlooking the dairy farms of Le Chefresne in Normandy have become a battleground in France’s efforts to boost power production.

In a corner of France known for Camembert cheese and apples, state-controlled Electricite de France SA plans to build 200 foot-tall steel pylons with high-voltage cables to carry electricity from a nuclear plant. The proposal would add to the 400,000 volts that pylons already carry from two existing reactors.

Posted in | »