On March 28, 2010, an electrical fault propagated by the failure of a bus-tie breaker to open resulted in a fire, and caused lowering voltage on 1 of 3 reactor coolant pumps (RCP), initiating a reactor trip. Due to the failure of the breaker to open to isolate the fault, power was lost to two buses. The subsequent cooldown resulted in an automatic safety injection initiation on low pressurizer pressure as operators focused on the fire. In following the procedure to restore the plant, operators attempted to reset the main generator lockout relay, which resulted in re-closing a separate breaker that had eventually opened to isolate the fault, re-energizing the fault and causing a second fire event in the switchgear. This resulted in grounds on the station's 2 DC buses. Further complications included a failure of the charging pump to swap suction sources from the Volume Control Tank to the Refueling Water Storage Tank on low level, and the closure of a Component Cooling Water (CCW) isolation valve to RCP thermal barrier heat exchanger which resulted in a temporary loss of CCW thermal barrier cooling for the RCP. The failure of the bus-tie breaker to open had been preceded by a loss of indicating lights for the control power associated with the breaker. The indicating lights had been unlit for months before the incident, but it was not recognized that this was indicative of an actual loss of control power to the breaker. The loss of control power resulted in the breaker not tripping which significantly complicated the incident. This event was originally rated a Level 1, however details that have come out during the NRC reactive inspection reviewing the incident, particularly regarding procedural deficiencies and inoperable equipment, have caused a re-evaluation of the incident as Level 2.
Big batteries and EVs to the rescue again as faults with new nuclear plant cause chaos on Nordic grids The Finnish nuclear power plant Olkiluoto was finally connected to the grid last year, at an estimated cost of €11 billion compared to the original budget of €3 billion. That cost blowout forced its developer, the […]
A vast subsea nuclear graveyard planned to hold Britain’s burgeoning piles of radioactive waste is set to become the biggest, longest-lasting and most expensive infrastructure project ever undertaken in the UK. The project [UK's nuclear waste dump] is now predicted to take more than 150yrs to complete with lifetime costs of £66bn in today’s money...The […]
Last year, the Dutch Province of Limburg started an alliance in which, besides the local government, research institutes, small nuclear reactor (SMR) developers, utilities, industrial customers and funders cooperated. With this "Limburg SMR alliance" Limburg tried to lead the way towards an SMR in Limburg. The preferred site for a first SMR would be Chemelot, […]
From the IPFM: During a visit to the Civaux nuclear power plant on 18 March 2024, France's Minister of the Armed Forces unveiled a plan to use the plant to produce tritium for the French nuclear weapons program. Civaux is a civilian power plant that belongs to and is operated by Electricité de France. According […]
An analysis by the Norwegian NGO Bellona of transborder trade operations with the customs code 840130 (irradiated fuel assemblies or fuel elements) show a more than twofold increase of import to EU countries of fresh nuclear fuel in cash terms – from 280 million Euros in 2022 to 686 million Euros in 2023. In physical […]