INES-event
INES 0

Events related to the earthquake on July 16th

Detailed investigation on all power reactors (units from #1 to #7) is still underway at Kashiwazaki-Kariwa nuclear power station. Nuclear and Industrial Safety Agency (NISA) of Japan, on November 13th, finalised the INES ratings for the four incidents which are found after the earthquake occurred on July 16th 2007. Other events including the bended ventilation duct found at Units #1 to #5, and water spillage on B5th floor of the reactor complex building of Unit #1 have been repaired and are considered to impose no risk of radioactive materials leakage.

[Incidents and INES ratings]
Unit #1 through #7,
Water of the spent fuel storage pool spread on the operation floor of the reactor buildings. INES 0.

Unit #6
Water with radioactive material found at 3 and 3M floors (uncontrolled area). INES 0

Unit #3
Fire at house transformer. Out of scale

Unit #6
Break of joints of drive shaft at the reactor building crane. Out of scale

Location: Kashiwazaki-Kariwa
Event date: Mon, 16-07-2007
Nuclear event report
Legenda & explanation